Upcoming RS-25 Engine Test Series Will Demo Lower Cost Rocket Engine Components for NASA's Artemis Program

Aerojet Rocketdyne and NASA are gearing up for a new phase of RS-25 hot-fire testing that will validate new components for the engine, which powers the core stage of the agency’s Space Launch System super heavy-lift exploration rocket.

The Retrofit-2 test series, consisting of seven tests at NASA’s Stennis Space Center, is expected to begin Jan. 28 and run through June. Each hot-fire test will last up to 500 seconds on the A1 Test Stand.

“This new hardware will significantly reduce the cost of the RS-25 rocket engine by leveraging important advances in design, materials and manufacturing technology,” said Eileen P. Drake, Aerojet Rocketdyne CEO and president.

Global Space Launch Systems - Market and Technology Forecast to 2027

Global Space Launch Systems - Market and Technology Forecast to 2027

Market forecasts by Region, Technology, Application, Orbit, Launch service, and Payload. Market and Technology Overview, and Leading Companies

Download free sample pages More information

Aerojet Rocketdyne is under contract to build 24 new engines, and the components being validated in this test series will be introduced in this production set. This new configuration will result in a 30% cost reduction in the RS-25 engine from the version that flew on the Space Shuttle.

Some of the components being demonstrated in the Retrofit-2 series were featured on the previous Retrofit-1B test campaign. These include a combustion chamber built using a high-tech brazing technique called Hot Isostatic Pressing (HIP), and an additively manufactured Pogo Accumulator Assembly, a beach ball-sized component that damps out liquid oxygen system pressure oscillations.

This test series will put a second HIP-bonded main combustion chamber through a comprehensive series of tests. Aerojet Rocketdyne chose a HIP-bonded design because it eliminates difficult and time consuming plating processes, reduces welding defects and costly rework. Development and certification models of the HIP-bonded combustion chamber have been completed and six production units are being assembled at Aerojet Rocketdyne.

The Retrofit-2 series will also continue to test the same Pogo hardware that was previously tested to further verify its durability. The additively manufactured Pogo assembly has already been tested 13 times, accumulating 5,400 seconds of total firing time. The additively manufactured Pogo design eliminates more than 20 parts, more than 100 welds and reduces fabrication time by more than 50%.

Retrofit-2 also will test two RS-25 high pressure fuel and oxidizer turbopumps built from simplified designs using modern techniques as well as 3D printed valves and redesigned actuators.


Aerojet Rocketdyne
View original News release

DoD Energy & Power Summit

DoD Energy & Power Summit

Washington, DC
Jul 31 - Aug 1, 2024

View agenda
SmallSat & Space Access Summit 2024

SmallSat & Space Access Summit 2024

National Harbor, MD
Jun 5 - 6, 2024

View agenda