Triumph Sails Marking End of an Era
Last T-Class Refit Draws to a Close
Read Market Research :
Undersea Warfare Systems 2009-2018
(March 4, 2010) -- Nuclear powered attack submarine (SSN) HMS Triumph sailed from Devonport Royal Dockyard today (Thursday 4 March) following a successful Long Overhaul Period (Refuel) [LOP(R)] by Babcock - the last Trafalgar class submarine refit and refuel to be undertaken.The extensive four year, 2.75 million manhour refit has included some significant capability improvements, as well as reactor refuelling, refurbishment work on all submarine systems, and addressing considerable emergent repair work.
Capability improvements have included installation of the latest sonar 2076 bow, flank and towed array systems, and upgrade for Tomahawk land attack cruise missile systems. A new command and control system has been installed, as well as a new internal fibre optic computer systems network and enhanced satellite communications system. An additional ballast pump has been installed to aid rapid deballasting, and a number of safety improvements incorporated to fire fighting and escape capabilities. Major equipments have been upgraded to support both efficiency and obsolescence management programmes, such as the chilled water plants.
The LOP(R), which saw some 30,000 work instructions raised and issued, and over 75,000 items of equipment overhauled, has included a number of challenges that were successfully met. Among these was the need for new inspection equipment to be designed, manufactured and commissioned to carry out surveys on the reactor systems. This required close working between Babcock, the MoD design authority and Rolls Royce to minimise programme impact. Additionally, repairs were successfully carried out by Babcock to both torpedo tube air ram cylinders which were far more extensive than anticipated before being surveyed at the start of the LOP(R). Further challenges included equipment obsolescence issues, often requiring fault diagnosis and resolution without original manufacturer's drawings.
Commenting on the LOP(R), Babcock submarine operations director, Devonport, Gavin Leckie, said: "The quality of HMS Triumph as she leaves for sea trials, and timely completion of this extensive refit, is testament to the skill, dedication, and close teamwork by all involved. The significant safety and capability improvements undertaken during this substantial overhaul programme have fully equipped the submarine for her next commission."
Superintendent Submarines, Captain Mike Robinson, said: "Despite this being the last Trafalgar Class submarine LOP(R) the project has had to overcome some significant emergent technical challenges and this has required close co-operation between the MoD and Babcock. The output of much hard work is an extremely capable submarine ready for her next commission."
HMS Triumph will now undergo a three month sea trials programme before returning to the Fleet for operational duties.
Source : Babcock International
MRO Military Europe Conference & Exhibition
London,United Kingdom
Sep 28 - 30, 2010
Register |
More info |
Send to friend |
More events
More News from Babcock International
-
Aug 24, 2010Babcock Wins Aerial Delivery System Contract
-
Jul 27, 2010Novel Approach to Submarine Support to Improve Availability ...
-
Jun 24, 2010UK MoD Awards GBP 45 M Contract for Over 140 Jackal 2a Vehic...
-
Jun 22, 2010500th Jackal Rolls Off Babcock Production Line
-
Jun 4, 2010HMS Blyth to Receive Upgrades at Rosyth
-
May 18, 2010Novel Defect Detection Technique to Be Used on T-Class Subma...
-
Apr 26, 2010Devonport Prepared to Receive Astute
More MRO
-
Sep 2, 2010BAE Receives $629 M to Upgrade Caiman MRAP
-
Sep 1, 2010CAE USA Wins USAF Contract to Upgrade C-5 Training Devices
-
Aug 31, 2010Boeing to Provide Landing Gear Exchange Service to Qantas Ai...
-
Aug 31, 2010VSE Awarded Contract by USMC for Corrosion Rehabilitation Fa...
-
Aug 30, 2010NGC Opens New Facility in Warner Robins
-
Aug 27, 2010US Military Continues Oshkosh Field Support for M-ATV
-
Aug 23, 2010Force Protection Receives $14.5 M Award for Field Service Su...
More Undersea Warfare
-
Aug 30, 2010Uk's Most Powerful Submarine Joins the Navy
-
Aug 26, 2010DRS Sonar Systems Awarded $9.7 M Contract
-
Aug 24, 2010Submariners Give Rare Glimpse Into 'Silent Service'
-
Aug 20, 2010Yellow Sea drill involves no aircraft carriers: US
-
Aug 19, 2010NGC Awarded $42 M for Fleet Support Work
-
Aug 19, 2010US, South Korea Announce Yellow Sea Exercise
-
Aug 18, 2010US steps up pressure on NKorea with anti-submarine drill


Print
Email
click to enlarge