Charles De Gaulle Refit and Upgrade
Published on ASDNews: Dec 8, 2008
Charles de Gaulle refit and upgrade : An exceptional shipyard project completed on timeThe CVN Charles de Gaulle refit and upgrade was completed on 1 December 2008. Prime contractor DCNS conducted this exceptional shipyard project at a sustained pace to complete it on time in just 15 months. The Group successfully coordinated the efforts of its own teams, subcontractors, the ship's crew and Navy fleet maintenance teams.
The main aims were to refurbish the ship and its systems, overhaul and refuel the nuclear reactors, modernise the command information and communication systems, and modify the ship to accommodate new weapon systems scheduled to be introduced in 2009, including Rafale combat aircraft to standard F3 and ASMP-A and Scalp Naval missiles.
"Thanks to flawless industrial organisation, DCNS as prime contractor completed the main refit tasks on time and on budget and without compromising working conditions or safety," says DCNS Executive Vice President & COO Bernard Planchais. "In engineering terms, the refuelling of the nuclear reactors represented a major first in view of the measures adopted to ensure complete nuclear safety. The industrial organisation was also exemplary as regards the pooling of expertise and skills by all parties, including the Navy, its Fleet Support Service (SSF), the ship's crew and an array of subcontractors led by Areva TA, not to mention the Group's own teams. The project's successful completion is a tribute to the professionalism of each and every team and to the Group's capacity to take on the most ambitious challenges," says Bernard Planchais.
After a refit and upgrade completed in the contractually agreed time of just 15 months, DCNS handed CVN Charles de Gaulle back to the French Navy which will now ramp the ship up to full operational readiness.
Source : DCNS
Offshore Patrol Vessels Summit
Norfolk, VA,United States
May 24 - 26, 2010
Register |
More info |
Send to friend |
More events
More News from DCNS
-
Mar 2, 2010DCNS Completes Perle Refit and Trials Ahead of Schedule
-
Nov 24, 2009DCNS to maintain French Navy's SSNs and SSBNs
-
Oct 15, 2009DCNS to Maintain French Navy's Front-Line Fighting Ships
-
Oct 9, 2009DCNS Prime Contractor for Europe's Largest Naval Defence Pro...
-
Oct 6, 2009DCNS to Supply Torpedo Countermeasures for French Submarine ...
-
Sep 11, 2009DCNS Completes 100th Sylver Vertical Missile Launcher
-
Sep 8, 2009DCNS Passes Major Milestone Towards One of Group's Biggest C...
More Ships
-
Mar 16, 2010Westminster On-Time, On-Budget
-
Mar 16, 2010Marinette Marine Facility Expansion to Enhance LM's LCS Prog...
-
Mar 12, 2010NGC to Supply IBS for New Indian Navy Fleet Tankers
-
Mar 12, 2010Aegis Weapon System Tested During International Multiple Shi...
-
Mar 12, 2010CIWS Upgrades Keep Lincoln Combat Ready
-
Mar 11, 2010US Navy Awards LM $17 M For MK 41 Vertical Launching System
-
Mar 11, 2010NGC to Supply Machinery Automation Systems on Mine Counterme...

Print this page
Send to friend