Soyuz' 1st launch campaign at Spaceport enters next phase of preparations

Soyuz Flight VS01 - Activities are in full swing across the Spaceport as its launch campaign for Soyuz' maiden flight from French Guiana moves ahead for the historic liftoff on October 20.

The mission's two Galileo navigation satellites have been integrated on the dispenser system that will deploy them during the mission, while the basic three-stage Soyuz launcher is undergoing final testing and checkout, and final validations of the launch pad are being completed.

Related Research on ASDReports.com:
Global Fixed Satellite Service (FSS) Market 2014-2018

Integration of the Galileo spacecraft on their dispenser occurred in the Spaceport's S5 payload preparation facility, where these European-built satellites also had been filled with propellant for their 12 years of operation in orbit.

The launch dispenser was developed for Arianespace by RUAG Space Sweden, and carries the satellites in a side-by-side arrangement. It will deploy the spacecraft four hours after launch by firing a pyrotechnic separation system to release them in opposite directions at the 23,222-km. orbital insertion point.

These satellites are the first of four In-Orbit Validation spacecraft to be launched by Soyuz, forming the operational nucleus of Europe's full 30-satellite Galileo navigation constellation being developed by the European Space Agency. The platforms were produced by EADS Astrium and have a launch mass of 700 kg. each. Program planning calls for the second set of two Galileo satellites to be orbited in 2012.

Separately, the Soyuz launcher's Fregat upper stage has been positioned on the integration stand in the Spaceport's S3B clean room facility, readying it to receive the Galileo satellites and their protective payload fairing - creating the mission's "upper composite."

In the Spaceport's northern sector, the ELS launch site also is alive with activity in preparation for the upcoming rollout of the basic three-stage Soyuz vehicle. The Soyuz is undergoing final testing inside its MIK launcher integration building, with the final checkout on schedule for an October 14 transfer to the launch pad. Once in the launch zone, the Soyuz will be raised to the vertical position for installation of the upper composite.

On the ELS launch pad itself, final verifications are now underway - including wrap-up functional and operational tests - in preparation for the Soyuz rollout this Friday.

The October 20 liftoff of Soyuz is set for 7:34 a.m. local time in French Guiana (10h34 UTC). This mission carries the "VS01" designation for Soyuz flights from the Spaceport, which will follow sequential numbering as the medium-lift vehicle joins Arianespace's heavy-lift Ariane 5 and the lightweight Vega - creating a complete launcher family.

Source : Arianespace

Published on ASDNews: Oct 11, 2011

 

Mobile MILSATCOM 2015

Mar 31 - Apr 1, 2015 - London, United Kingdom

Register More info


© 2004-2014 • ASDNews • be the first to know • contact usterms & conditionsprivacy policyadvertisingfaqs

zpsk